Barnes Hospital specialist school now due to open in September 2027

2 min read
Tom Ashworth
20 November 2026

London River Academy, 90 places for children with social, emotional and mental health needs, has missed two target dates. This time there is a half-built school behind the promise.

Builders passed the halfway mark in July, which makes this the most credible date yet.

A specialist school for up to 90 children on the former Barnes Hospital site is now expected to open in September 2027, Richmond Council has confirmed.

London River Academy will take pupils aged seven to 19 with social, emotional and mental health needs, and will be run by The Beckmead Trust. The date followed a council committee discussion on 12 November.

It is the third date families have been given. The school was first hoped for 2024, then 2025. Plans were approved in 2023, and the Department for Education is leading the project. No source we found explains the delays, and September 2027 is the council's expected date rather than a firm commitment from the Department or the Trust.

What gives this date more weight is the building work. Contractor Willmott Dixon marked the halfway point of the £30m Barnes Hospital regeneration on 27 July and said both new buildings are due to open in 2027. The second is an NHS building for community mental health services, which moved to Livingston House in Teddington in 2023.

The project website describes a three-storey teaching block, a double-height hall and a single-storey block on the southern part of the site, stepping down towards the southern boundary. There will be 15 classrooms of up to eight pupils each.

Until then, the council's stopgap is a temporary centre at Nelson Primary School in Whitton, set up in September 2025 for up to 45 secondary pupils.

Demand explains the urgency. Richmond now has 393 state-funded specialist places, up from 159 in 2012. In September the council opened a new centre in Petersham with 78 places and another in Hampton with 24. Officers plan an audit of specialist provision and two new resource bases in secondary schools.

For families who have watched the date slip twice, a half-built school is better news than another press release. The next question is how many of the 90 places go to children from Barnes and the rest of Richmond borough, and what becomes of the Nelson Primary centre once the new school opens.

The facts
  • London River Academy is a school for up to 90 pupils aged 7 to 19 with SEMH needs, run by The Beckmead Trust.
  • Richmond Council has confirmed an expected opening of September 2027.
  • It was originally hoped to open by 2024, then 2025; plans were approved in 2023.
  • The building has 15 classrooms (three primary, nine secondary, three post-16), each for up to eight pupils.
  • Willmott Dixon marked the halfway point of the £30m Barnes Hospital regeneration on 27 July 2026.
  • A temporary SEMH centre at Nelson Primary School, Whitton, has served up to 45 secondary pupils since September 2025.
  • Richmond has 393 state-funded specialist places, up from 159 in 2012.
Sources and evidence

Every factual claim in this story is linked to the evidence behind it. Where the newsroom has added judgement or framing, it is listed separately. Sources accessed 20 November 2026.

  1. Nub News (LDRS): Date set for new specialist school (media)
  2. South London: New Richmond specialist school to finally open in 2027 (media)
  3. Former Barnes Hospital: London River Academy (other)
  4. Willmott Dixon: halfway point at Barnes Hospital (business)
Claim by claim (7 facts, 7 editorial judgements)
  • Richmond Council has confirmed the school's expected opening is September next year (2027). — media, 2026-11-17
    “Richmond Council has now confirmed its expected opening has been pushed to next September.”
  • The school is for up to 90 pupils aged seven to 19 and will be run by The Beckmead Trust. — media, 2026-11-17
    “run by The Beckmead Trust for up to 90 pupils aged seven to 19”
  • The school was originally hoped to open by 2024, then 2025, and has faced a series of delays; plans were approved in 2023 and the DfE leads the project. — media, 2026-11-17
    “originally hoped the specialist school would open by 2024, then 2025... has faced a series of delays.”
  • Richmond Council set up a temporary SEMH centre at Nelson Primary School in Whitton in September 2025 for up to 45 secondary pupils. — media, 2026-11-17
    “temporary SEMH centre at Nelson Primary School in Whitton for up to 45 secondary pupils”
  • Richmond has 393 state-funded specialist places, up from 159 in 2012; new Petersham (78 places) and Hampton (24 places) centres opened in September; 14 resource bases exist; officers plan an audit and two new secondary resource bases; the committee discussed the report on 12 November. — media, 2026-11-17
    “393 this year, up from 159 in 2012”
  • The building has a three-storey teaching block, double-height hall, single-storey ancillary block and 15 classrooms for up to eight pupils each, on the southern part of the site, stepping down toward the southern boundary. — other
    “Beckmead Trust have been selected to operate the school.”
  • Willmott Dixon marked the halfway point of the £30m regeneration on 27 July 2026; both buildings are due to open in 2027; the NHS building is for community mental health services that moved to Livingston House, Teddington in 2023. — business, 2026-07-27
    “due to open in 2027”
  • Judgement: No source found gives a reason for the delays; the date is the council's expected date, not a DfE or Trust commitment.
  • Judgement: It is the third date families have been given.
  • Judgement: What gives this date more weight is the building work.
  • Judgement: Demand explains the urgency.
  • Judgement: For families who have watched the date slip twice, a half-built school is better news than another press release.
  • Judgement: Builders passed the halfway mark in July, which makes this the most credible date yet.
  • Judgement: The next question is how many of the 90 places go to children from Barnes and the rest of Richmond borough, and what becomes of the Nelson Primary centre.
London River Academy, Barnes Hospital site: opening 2027 · The Barnes Times